We’re kicking off the new year by checking in on BC Retreat! Last time we did an update on this project, windows install had started and the house wrap had gone up. Since then, most of the windows have been fully installed and siding install is progressing well.
In addition to the main house, we’ve begun work on the pool house. We’ve designed the pool to be on axis with the screen porch and the main fireplace, with the pool house at the other end. We’ve poured the slab and foundation for the pool house and excavation and the concrete pour for the the pool have also been completed. We’re excited to see the whole site and house coming together and to be able to really envision the finished product! Check out some recent photos and a quick timelapse of some of the recent progress!